• Expert Services
  • Geotechnics
  • Storage / Environment / Sustainability
  • Waterproofing
Show All Projects

London Cable Replacement Tunnels

National Grid

National Grid is currently undertaking a major cable replacement program in the area of London to serve the increasing energy demand for the city. Part of that investment is the installation of high-voltage underground cables in a series of tunnels to be built between Hackney and Willesden.

Engineering Consulting and Design Services:

Gall Zeidler Consultants (GZ) has been contracted to carry out a Category 3 Check of the design for the excavation and primary lining of the tunnel adit at the Willesden Shaft. Additionally, GZ was responsible for the temporary designs of the Islington Shaft Launch Adit, the St. Pancras Shaft Launch Adit, and the temporary and permanent designs of the Wandsworth Adits, St. Johns Woods Adits, the Finsbury Park Chambers, the Islington Chamber, and the St. Pancras Chamber. During the construction of the chambers, GZ is scheduled to have design representation, which will provide quality assurance and quality control for the Contractor.

The adit has a diameter of approximately 16 feet (4.8 meters) and is located approximately 80 feet (24 meters) below ground level in London Clay. The groundwater table elevation varies from site to site, but rangeds from approximately 6.6 feet (2 meters) to 16.4 feet (5 meters) below the ground surface. The adits and chambers will be constructed using Sprayed Concrete Lining / Sequential Excavation Method (SCL / SEM). The permanent linings for the structures included both sprayed concrete and cast-in-place methods.

The consulting and design services include Two-and Three-Dimensional Finite Element Models (FEM) to determine requirements for the sprayed concrete lining and cast-in-place elements during all construction stages in accordance with the project specifications and Eurocode.

Location:

London, United Kingdom

Date:

2011 – Present

Structure:

Temporary TBM Launch and Reception Adits; Diversion Chambers

Length:

TBM Launch and Reception Adits: 33 to 197 feet (10 to 60 meters); Transition Tunnels: 21 to 36 feet (6.3 to 10.9 meters); Junction Tunnels: 36 to 66 feet(10.9 to 20.2 meters); Diversion Chambers: 15 to 35 feet (4.5 to 10.6 meters)

Cross-Section:

TBM Launch and Reception Adits: 194 to 291 square feet (18 to 27 square meters); Junction Tunnels: 538 to 646 square feet (50 to 60 square meters); Diversion Chambers: 388 to 517 square feet (36 to 48 square meters)

Geology:

London Clay, Lambeth Group; Groundwater table is approximately 6.6 to 14.6 feet (2 to 5 meters) below surface

Cost:

Approximately US $351 Million

Client:

Costain Ltd.

Owner:

National Grid